Difficulty: Hard
A+B finish a job in 8 days, B+C in 12 days, and C+A in 16 days. How long would A take alone?
A 18 days
B 20 days
C 24 days
D 19.2 days
Answer: D. 19.2 days. A’s rate is ½(1/8+1/16−1/12) = 5/96; time is 96/5 = 19.2 days.
A, B and C take 20, 30 and 60 days alone. How long do they take together?
A 10 days
B 8 days
C 12 days
D 15 days
Answer: A. 10 days. Their rates sum to 1/20+1/30+1/60 = 1/10 per day.
A takes 24 days. B is 50% more efficient than A. How long do they take together?
A 8 days
B 9.6 days
C 10 days
D 12 days
Answer: B. 9.6 days. B takes 16 days; combined rate is 1/24+1/16 = 5/48.
Twelve workers can finish in 18 days. After 6 days, 4 more workers join. What is the total duration?
A 14 days
B 16 days
C 15 days
D 18 days
Answer: C. 15 days. The total is 216 worker-days; 72 are done; 144 remain for 16 workers, taking 9 days.
A and B complete 3/4 of a task in 9 days. A alone takes 16 days. How long would B alone need?
A 36 days
B 40 days
C 60 days
D 48 days
Answer: D. 48 days. The combined rate is 1/12; B’s rate is 1/12−1/16 = 1/48.
A takes 18 days and B 24 days. What fraction do they complete together in 3 days?
A 7/24
B 1/4
C 5/18
D 1/3
Answer: A. 7/24. Their combined rate is 1/18+1/24 = 7/72; in 3 days they complete 7/24.
Thirty machines working 8 hours daily finish a job in 12 days. How long would 24 machines working 10 hours daily take?
A 10 days
B 12 days
C 15 days
D 18 days
Answer: B. 12 days. Both teams provide 240 machine-hours per day, so the duration remains 12 days.
A works alone in 12 days and B in 18 days. They alternate full days, starting with A. When is the job completed?
A 13 days
B 14 days
C 14 1/3 days
D 15 days
Answer: C. 14 1/3 days. Each two-day cycle completes 5/36; after 14 days 35/36 is done; A finishes the last 1/36 in 1/3 day.
A takes 16 days and B takes 24 days. A works alone for 4 days, then B completes the rest. What is the total time?
A 18 days
B 20 days
C 24 days
D 22 days
Answer: D. 22 days. A completes 1/4; B takes 18 days for the remaining 3/4; total 22.
Ten machines working 6 hours daily finish a task in 12 days. How many machines working 9 hours daily finish it in 8 days?
A 10
B 8
C 12
D 15
Answer: A. 10. The job is 10×6×12 = 720 machine-hours; 8×9 = 72 hours per machine, so 10 machines.
A takes 30 days and B 20 days. A works alone for 6 days, then both work together. What is the total time?
A 14 days
B 15.6 days
C 16 days
D 18 days
Answer: B. 15.6 days. A completes 1/5; the remaining 4/5 at 1/12 per day takes 9.6 more days.
A and B together finish in 12 days. A alone takes 20 days. How long does B take alone?
A 24 days
B 36 days
C 30 days
D 40 days
Answer: C. 30 days. B’s rate is 1/12−1/20 = 1/30 per day.
A is twice as efficient as B. Together they finish in 6 days. How long would A take alone?
A 8 days
B 12 days
C 18 days
D 9 days
Answer: D. 9 days. A:B rates are 2:1; A supplies 2/3 of the combined rate, so its rate is 1/9.
A completes 40% of a job in 8 days. B completes the remaining 60% in 12 days. What is the ratio of their daily rates A:B?
A 1:1
B 2:3
C 3:2
D 4:5
Answer: A. 1:1. A’s rate is 0.40/8 = 0.05; B’s is 0.60/12 = 0.05.
A and B together complete 1/3 of a job in 4 days. A alone takes 20 days. How long does B take alone?
A 24 days
B 30 days
C 36 days
D 40 days
Answer: B. 30 days. Combined rate is 1/12; B’s rate is 1/12−1/20 = 1/30.
Ten women or six men can finish a job in 15 days. How long would 2 men and 5 women take?
A 15 days
B 20 days
C 18 days
D 24 days
Answer: C. 18 days. Six men equal ten women; 2 men plus 5 women equal 25/3 women; 150÷(25/3) = 18 days.
A finishes in 40 days. B is 25% more efficient than A. How long do they take together?
A 16 days
B 18 days
C 20 days
D 17 7/9 days
Answer: D. 17 7/9 days. B needs 32 days; combined rate is 1/40+1/32 = 9/160; time is 160/9.
Fifteen workers plan to finish in 12 days. After 4 days, 5 leave. What is the total duration?
A 16 days
B 14 days
C 18 days
D 20 days
Answer: A. 16 days. Total work is 180 worker-days; 60 are done; 120 remain for 10 workers, taking 12 days.
A takes 20 days and B 30 days. B works alone for 5 days, then both work together. What is the total time?
A 12 days
B 15 days
C 16 days
D 18 days
Answer: B. 15 days. B completes 1/6; remaining 5/6 at combined rate 1/12 takes 10 days.
Thirty workers complete 2/3 of a job in 8 days. How many workers are needed to finish the rest in 2 days?
A 45
B 50
C 60
D 75
Answer: C. 60. The remaining 1/3 is 120 worker-days; 120÷2 = 60 workers.
A and B together finish in 16 days. B alone takes 48 days. How long does A need alone?
A 20 days
B 30 days
C 32 days
D 24 days
Answer: D. 24 days. A’s rate is 1/16−1/48 = 1/24 per day.
Twelve people need 24 days for a job. After 8 days, 4 more join. What is the total duration?
A 20 days
B 18 days
C 21 days
D 24 days
Answer: A. 20 days. Total work is 288 person-days; 96 are done; 192 remain for 16 people, taking 12 days.
A completes 40% of a task in 8 days and B completes 60% in 9 days. What is the ratio of B’s rate to A’s?
A 3:4
B 4:3
C 5:4
D 2:1
Answer: B. 4:3. A’s rate is 1/20; B’s is 1/15; B:A = 20:15 = 4:3.
Twenty workers finish 75% of a job in 15 days. How many days would 30 workers need for the rest?
A 3 days
B 4 days
C 3 1/3 days
D 5 days
Answer: C. 3 1/3 days. The remaining quarter is 100 worker-days; 100÷30 = 3 1/3 days.
A takes 24 days and B takes 36 days. What fraction remains after they work together for 8 days?
A 1/3
B 5/9
C 2/3
D 4/9
Answer: D. 4/9. Their rate is 1/24+1/36 = 5/72; in 8 days they do 5/9, leaving 4/9.