A can complete a job in 10 days. What fraction does A complete in one day?
A 1/10
B 1/5
C 1/8
D 1/12
Answer: A. 1/10. One day’s work is the reciprocal of 10 days.
A finishes a job in 12 days and B in 6 days. How long do they take together?
A 3 days
B 4 days
C 6 days
D 9 days
Answer: B. 4 days. Their daily rates add to 1/12+1/6 = 1/4 job per day.
A completes 1/5 of a job each day. How many days are needed for the whole job?
A 4 days
B 6 days
C 5 days
D 10 days
Answer: C. 5 days. Five portions of 1/5 complete the job.
A completes a job in 20 days. What fraction is finished in 5 days?
A 1/5
B 1/3
C 1/2
D 1/4
Answer: D. 1/4. Five days is 5/20 = 1/4 of the required time.
Four workers finish a task in 10 days. How many worker-days does the task require?
A 40
B 14
C 30
D 50
Answer: A. 40. Worker-days = 4×10 = 40.
Six people can finish a job in 12 days. How long would 3 people need at the same rate?
A 18 days
B 24 days
C 20 days
D 30 days
Answer: B. 24 days. The work is 6×12 = 72 person-days; 72÷3 = 24.
A completes a job in 15 days. What fraction is done after 5 days?
A 1/5
B 1/2
C 1/3
D 2/3
Answer: C. 1/3. Five days is one-third of 15 days.
Eight workers complete a job in 6 days. How many worker-days is this?
A 14
B 42
C 56
D 48
Answer: D. 48. 8×6 = 48 worker-days.
A can finish in 10 days and B in 15 days. How long do they take together?
A 6 days
B 5 days
C 8 days
D 12 days
Answer: A. 6 days. Their combined daily rate is 1/10+1/15 = 1/6.
Twelve workers finish a task in 8 days. How long would 6 workers take?
A 12 days
B 16 days
C 14 days
D 20 days
Answer: B. 16 days. Half as many workers need twice the time: 12×8÷6 = 16.
A completes 1/8 of a job each day. How long does the whole job take?
A 6 days
B 10 days
C 8 days
D 12 days
Answer: C. 8 days. Eight daily portions of 1/8 make one whole job.
Five workers make 100 units in 4 days. How many units does one worker make per day?
A 4
B 6
C 10
D 5
Answer: D. 5. Output per worker-day is 100÷(5×4) = 5 units.
A completes 1/4 of a job in 3 days. How many days would the whole job take?
A 12 days
B 9 days
C 15 days
D 18 days
Answer: A. 12 days. Four times 3 days are needed for four quarters.
Nine people finish a task in 6 days. How many person-days is the work?
A 15
B 54
C 45
D 60
Answer: B. 54. 9×6 = 54 person-days.
B can finish a job in 3 days. What fraction of the job does B complete each day?
A 1/2
B 1/4
C 1/3
D 1/6
Answer: C. 1/3. One whole job divided over 3 days is 1/3 per day.
A takes 20 days and B takes 30 days to finish a job alone. How long together?
A 10 days
B 15 days
C 25 days
D 12 days
Answer: D. 12 days. Their combined rate is 1/20+1/30 = 1/12 job per day.
Three workers finish a job in 6 days. How long would 6 workers need?
A 3 days
B 2 days
C 4 days
D 12 days
Answer: A. 3 days. Doubling workers halves the time: 3×6÷6 = 3 days.
Four people finish a job in 12 days. How long would 8 people need?
A 4 days
B 6 days
C 8 days
D 10 days
Answer: B. 6 days. The work is 48 person-days; 48÷8 = 6 days.
A can complete a task in 24 days. What fraction is done in 8 days?
A 1/4
B 1/2
C 1/3
D 2/3
Answer: C. 1/3. 8/24 simplifies to 1/3.
A takes 18 days and B takes 9 days alone. How long do they take together?
A 4.5 days
B 9 days
C 12 days
D 6 days
Answer: D. 6 days. Their rates sum to 1/18+1/9 = 1/6 per day.
Seven workers finish a task in 7 days. How many worker-days is that?
A 49
B 14
C 42
D 56
Answer: A. 49. 7×7 = 49 worker-days.
Four workers finish a task in 9 days. How long would 3 workers need?
A 10 days
B 12 days
C 14 days
D 18 days
Answer: B. 12 days. The work is 36 worker-days; 36÷3 = 12.
A completes 1/6 of a job per day. What fraction is done in 3 days?
A 1/3
B 2/3
C 1/2
D 5/6
Answer: C. 1/2. 3×1/6 = 3/6 = 1/2.
A takes 12 days and B takes 24 days. How long do they take together?
A 6 days
B 9 days
C 12 days
D 8 days
Answer: D. 8 days. Their combined rate is 1/12+1/24 = 1/8 per day.
Two workers finish a job in 30 days. How long would 5 workers take?
A 12 days
B 10 days
C 15 days
D 18 days
Answer: A. 12 days. The job is 60 worker-days; 60÷5 = 12.