Difficulty: Easy & Basic
A completes a job in 8 days and B in 12 days. How long do they take together?
A 4 days
B 4.8 days
C 5 days
D 6 days
Answer: B. 4.8 days. Combined rate is 1/8+1/12 = 5/24; time is 24/5 = 4.8 days.
Fifteen workers finish a task in 12 days. How long would 20 workers need?
A 8 days
B 10 days
C 9 days
D 15 days
Answer: C. 9 days. Work is 15×12 = 180 worker-days; 180÷20 = 9.
A finishes a task in 12 days. What fraction remains after A works 3 days?
A 1/4
B 1/2
C 2/3
D 3/4
Answer: D. 3/4. A completes 3/12 = 1/4; the remaining work is 3/4.
Six workers complete a job in 8 days. How long would 4 workers need?
A 12 days
B 10 days
C 14 days
D 16 days
Answer: A. 12 days. The job is 48 worker-days; 48÷4 = 12.
A and B together finish in 10 days. A alone needs 15 days. How long does B alone need?
A 20 days
B 30 days
C 25 days
D 40 days
Answer: B. 30 days. B’s rate is 1/10−1/15 = 1/30 per day.
Six workers make 180 units in 5 days. How many units does one worker make per day?
A 5
B 8
C 6
D 10
Answer: C. 6. 180÷(6×5) = 6 units per worker-day.
A completes 1/5 of a job each day. What fraction is done in 4 days?
A 1/2
B 3/5
C 1
D 4/5
Answer: D. 4/5. Multiply the daily rate by 4: 4×1/5 = 4/5.
Three workers take 15 days for a job. How many days would 5 workers take?
A 9 days
B 8 days
C 10 days
D 12 days
Answer: A. 9 days. The job is 45 worker-days; 45÷5 = 9.
A takes 10 days, B 15 days and C 60 days. How long do all three take together?
A 4 days
B 5 days
C 6 days
D 8 days
Answer: B. 5 days. Their rates sum to 1/10+1/15+1/60 = 1/5 per day.
A completes a job in 25 days. B works twice as fast as A. How long does B need?
A 10 days
B 15 days
C 12.5 days
D 20 days
Answer: C. 12.5 days. Twice the rate takes half the time: 25÷2 = 12.5.
Twelve workers work 8 hours a day for 10 days. How many days would 16 workers need at 6 hours a day?
A 8 days
B 12 days
C 15 days
D 10 days
Answer: D. 10 days. Total effort is 12×8×10 = 960 worker-hours; daily capacity is 16×6 = 96; time is 10 days.
Twenty machines make 400 pieces in 5 days. How many pieces do 16 machines make in 5 days?
A 320
B 280
C 360
D 400
Answer: A. 320. Output is proportional to machine count: 400×16/20 = 320.
A team completes 40% of a job in 8 days. How many days would it take for the whole job?
A 16 days
B 20 days
C 24 days
D 32 days
Answer: B. 20 days. One percent takes 8/40 day; 100% takes 20 days.
Ten workers need 18 days for a job. After 6 days, 4 workers leave. How many more days do the remaining workers need?
A 16 days
B 18 days
C 20 days
D 24 days
Answer: C. 20 days. Total is 180 worker-days; 60 are done; 120 remain for 6 workers, taking 20 days.
A takes 12 days and B takes 6 days. A works alone for 3 days, then B joins. What is the total time?
A 5 days
B 7 days
C 8 days
D 6 days
Answer: D. 6 days. A does 1/4; remaining 3/4 at combined rate 1/4 per day takes 3 more days.
A and B finish a job together in 8 days. A alone takes 12 days. How long does B alone need?
A 24 days
B 16 days
C 20 days
D 32 days
Answer: A. 24 days. B’s rate is 1/8−1/12 = 1/24 of the job per day.
Five workers start an 8-day job. After 4 days, two leave. How many more days do the remaining workers need?
A 5 days
B 6 2/3 days
C 7 days
D 8 days
Answer: B. 6 2/3 days. Half the work remains: 20 worker-days; 20÷3 = 6 2/3 days.
Eight workers work 6 hours daily for 10 days. How long would 12 workers working 8 hours daily need?
A 6 days
B 8 days
C 5 days
D 10 days
Answer: C. 5 days. Work is 480 worker-hours; new daily capacity is 96 worker-hours.
A team finishes 25% of a job in 5 days. How long would the entire job take?
A 15 days
B 18 days
C 25 days
D 20 days
Answer: D. 20 days. Four times as much work needs 4×5 = 20 days.
Twelve people complete work in 15 days. How many days would 18 people need?
A 10 days
B 8 days
C 12 days
D 18 days
Answer: A. 10 days. Work is 180 person-days; 180÷18 = 10.
B is 50% more efficient than A. If A needs 24 days, how long does B need?
A 12 days
B 16 days
C 18 days
D 20 days
Answer: B. 16 days. B’s rate is 1.5 times A’s; time is 24÷1.5 = 16 days.
Four workers finish a job in 15 days. How many days would 10 workers need?
A 5 days
B 8 days
C 6 days
D 10 days
Answer: C. 6 days. Work is 60 worker-days; 60÷10 = 6.
A takes 15 days and B takes 30 days. How long do they take together?
A 8 days
B 12 days
C 15 days
D 10 days
Answer: D. 10 days. Combined rate is 1/15+1/30 = 1/10 per day.
A team completes 30% of a task in 9 days. How long does the whole task take?
A 30 days
B 27 days
C 32 days
D 36 days
Answer: A. 30 days. The full work takes 9÷0.30 = 30 days.
Twelve workers plan to finish in 20 days. After 10 days, 6 more join. What is the total time?
A 15 days
B 16 2/3 days
C 17 days
D 18 days
Answer: B. 16 2/3 days. The first half is done; remaining work is 120 worker-days, completed by 18 workers in 6 2/3 days.