Production engineering aims to make products how?
A Only by hand
B Without quality checks
C Efficiently and economically
D At maximum cost
Answer: C. Efficiently and economically. Production engineering designs manufacturing methods that meet quality, cost and delivery needs.
Process planning defines what for a part?
A Manufacturing sequence
B Marketing budget
C Supplier ownership
D Employee vacation plan
Answer: A. Manufacturing sequence. Process planning selects and orders operations, machines and resources for manufacture.
An operation sheet records process steps and what?
A Product advertising
B Customer invoices
C Work instructions
D Inventory valuation only
Answer: C. Work instructions. An operation sheet documents the sequence and key instructions for production operations.
A product layout is suited to what production volume?
A One-off repair work
B Low variety job shop
C Custom prototypes only
D High volume
Answer: D. High volume. Product layout arranges stations in operation sequence for repetitive high-volume production.
A process layout groups machines by what?
A Similar function
B Product sequence
C Customer name
D Batch color
Answer: A. Similar function. Process layouts group similar equipment, as in a job shop.
Cellular layout groups resources around what?
A All suppliers
B Finished goods only
C Employee shifts
D Part families
Answer: D. Part families. Cellular manufacturing groups machines to process families of similar parts.
Line balancing assigns tasks to stations to reduce what?
A Product quality
B Idle time
C Customer demand
D Material strength
Answer: B. Idle time. Line balancing distributes work among stations to match cycle time and reduce imbalance.
Cycle time is time between successive what?
A Machine repairs
B Supplier orders
C Completed units
D Shift changes
Answer: C. Completed units. Cycle time is the interval between consecutive finished units at a process.
Takt time equals available production time divided by what?
A Machine count
B Customer demand
C Inventory value
D Supplier lead time
Answer: B. Customer demand. Takt time sets the production pace needed to meet demand.
A bottleneck limits which system measure?
A Product color
B Material density
C Machine footprint
D Throughput
Answer: D. Throughput. The system bottleneck constrains achievable output rate.
Capacity utilization compares actual output with what?
A Customer complaints
B Design capacity
C Scrap mass
D Supplier count
Answer: B. Design capacity. Utilization is actual production divided by available or design capacity.
Batch production makes items in what pattern?
A Groups of units
B One continuous unique item
C No repeated items
D Only one unit ever
Answer: A. Groups of units. Batch production processes a group of identical items before changing over.
Mass production typically uses which arrangement?
A Product flow line
B Random job shop
C Single custom bench
D Project network only
Answer: A. Product flow line. Mass production uses repetitive standardized processes and dedicated flow.
Job production is best for what demand?
A Very high standard volume
B Low-volume customization
C Continuous commodity flow
D One fixed product forever
Answer: B. Low-volume customization. Job production handles varied, customized work in small quantities.
Just-in-time production seeks to reduce what?
A Product quality
B Customer value
C Unneeded inventory
D Machine capability
Answer: C. Unneeded inventory. JIT aims to make and deliver only what is needed when needed.
Kanban is commonly used as what?
A Push forecast
B Quality certificate
C Machine guard
D Pull signal
Answer: D. Pull signal. Kanban signals replenishment or production in a pull system.
Material requirements planning uses demand and what inputs?
A Control chart
B Process capability
C Bill of materials
D Machine layout only
Answer: C. Bill of materials. MRP calculates component needs from the master schedule, inventory and bill of materials.
A bill of materials lists product what?
A Machine speeds
B Operator skills
C Inspection results
D Components and quantities
Answer: D. Components and quantities. The BOM lists components, subassemblies and required quantities.
A routing specifies which sequence?
A Customer payment steps
B Operations through shop
C Quality audit cycle
D Employee training plan
Answer: B. Operations through shop. Routing defines the production path and operation sequence for a part.
Work study combines method study with what?
A Product design
B Inventory valuation
C Preventive maintenance
D Work measurement
Answer: D. Work measurement. Work study improves methods and establishes time standards.
Standard time usually includes normal time plus what?
A Allowances
B Scrap cost
C Setup cost only
D Machine depreciation
Answer: A. Allowances. Standard time adds appropriate personal, fatigue and delay allowances to normal time.
A learning curve predicts unit time changes with what?
A Cumulative production
B Inventory age
C Tool diameter
D Shift temperature
Answer: A. Cumulative production. Learning effects reduce average task time as cumulative output increases.
Ergonomic workstation design considers worker capability and what?
A Only machine color
B Task demands
C Supplier location
D Product packaging only
Answer: B. Task demands. Ergonomics fits tasks and workplaces to human abilities and limitations.
Value-stream mapping depicts material flow and what?
A Only plant ownership
B Product color
C Information flow
D Machine depreciation
Answer: C. Information flow. A value stream map shows material and information from request to delivery.
A production system transforms inputs into what?
A Goods or services
B Only inventory
C Only machine hours
D Supplier contracts
Answer: A. Goods or services. Production systems convert resources into products or services.