Five failures occur over 10,000 operating hours. What is MTBF?

A 1,000 h
B 2,000 h
C 5,000 h
D 10,000 h

With constant failure rate and MTBF=1,000 h, what is reliability at 200 h?

A 0.67
B 0.90
C 0.98
D 0.82

MTBF is 900 h and MTTR is 10 h. What is steady-state availability?

A 98.9%
B 90.0%
C 95.0%
D 99.9%

An item has MTBF of 2,500 h. What constant failure rate is estimated?

A 0.0002/h
B 0.0020/h
C 0.0004/h
D 0.0040/h

An FMEA uses severity 8, occurrence 3, detection 2. What is RPN?

A 24
B 32
C 64
D 48

Two independent series components have reliabilities 0.98 and 0.99. What is system reliability?

A 0.950
B 0.970
C 0.985
D 0.999

Parallel redundant units have reliabilities 0.90 and 0.80. What is combined reliability?

A 0.72
B 0.90
C 0.98
D 0.96

A 100 NΒ·m target uses a 0.4 m wrench and 0.1 m inline extension. What wrench setting is needed?

A 80 NΒ·m
B 64 NΒ·m
C 100 NΒ·m
D 125 NΒ·m

An extension is placed at 90Β° to a torque wrench. What happens to effective length?

A It doubles
B It halves
C It becomes zero
D It is unchanged

A part has a 3,000-cycle life limit and has used 2,740 cycles. How many remain?

A 160
B 260
C 240
D 360

Independent fault events have probabilities 0.10 and 0.20. What is AND-gate probability?

A 0.02
B 0.10
C 0.28
D 0.30

The same events feed an OR gate. What is OR probability?

A 0.02
B 0.20
C 0.28
D 0.30

A monitored component shows a steady vibration rise but remains below limit. What is the sound next step?

A Ignore until failure
B Remove all sensors
C Reset the limit
D Trend and investigate

A component is nearing its approved life limit. What is the correct planning action?

A Extend life informally
B Schedule timely replacement
C Erase cycle records
D Wait for a defect

Severe corrosion is found in a concealed area. What guides treatment?

A Approved corrosion data
B General cleaning only
C Unverified shop practice
D Paint color chart

After corrosion removal, what should be restored?

A Bare metal surface
B Unsealed lap joint
C Approved protective finish
D Damaged primer

A flight-control linkage is opened during maintenance. What may be required before release?

A Paint thickness check
B Fuel sample
C Cabin pressure test
D Independent inspection

A torque wrench is dropped or overloaded. What action protects measurement integrity?

A Keep using it
B Recalibrate or inspect
C Increase torque setting
D Remove serial number

A repeated defect appears after each flight. Which data should be analyzed first?

A Discrepancy and repair history
B Passenger manifest
C Paint batch only
D Route map

A maintenance task is interrupted mid-step. What reduces restart error?

A Rely on memory
B Remove the task card
C Mark status and next step
D Close the work order

An NDI indication is near an acceptance threshold. Who should evaluate it?

A Any available technician
B Parts vendor only
C Aircraft owner alone
D Qualified personnel using criteria

A functional test passes but the original defect remains intermittent. What should follow?

A Close the discrepancy
B Continue fault isolation
C Erase fault history
D Replace unrelated parts

Why should maintenance findings be fed into reliability analysis?

A Identify recurring patterns
B Reduce documentation
C Remove scheduled tasks
D Change aircraft identity

An aircraft receives a new maintenance instruction. What should technicians use?

A Old printed copy
B Uncontrolled summary
C Current approved revision
D Memory alone

A task is signed off without required inspection evidence. What is missing?

A Aircraft configuration
B Fuel quantity
C Tool storage
D Documented verification