A 1:500 site plan shows 86 mm between points. Find ground distance.
A 43 m
B 4.3 m
C 17.2 m
D 430 m
Answer: A. 43 m. Ground distance is 86 mm times 500, or 43,000 mm, equal to 43 m.
A design resistance is 480 kN and applied demand is 320 kN. Find factor of safety.
A 1.5
B 0.67
C 1.0
D 2.0
Answer: A. 1.5. The ratio of resistance to demand is 480 divided by 320, or 1.5.
A 12 m by 9 m slab is 180 mm thick. Find concrete volume.
A 9.72 mΒ³
B 19.44 mΒ³
C 18 mΒ³
D 194.4 mΒ³
Answer: B. 19.44 mΒ³. Convert thickness to 0.18 m; volume is 12 times 9 times 0.18, or 19.44 cubic metres.
Using Q=0.00278 C i A, find Q for C 0.7, i 80 mm/h, A 5 ha.
A 0.078 mΒ³/s
B 0.779 mΒ³/s
C 0.389 mΒ³/s
D 1.56 mΒ³/s
Answer: B. 0.779 mΒ³/s. The estimate is 0.00278 times 0.7 times 80 times 5, about 0.779 cubic metres per second.
A simply supported 8 m beam carries a uniform 20 kN/m load. Find peak moment.
A 80 kNΒ·m
B 120 kNΒ·m
C 320 kNΒ·m
D 160 kNΒ·m
Answer: D. 160 kNΒ·m. For a simply supported beam under uniform load, maximum moment is wL squared divided by 8: 20 times 64 divided by 8 is 160 kNΒ·m.
With specified factors 1.2D and 1.6L, D is 200 kN and L is 100 kN. Find factored load.
A 280 kN
B 400 kN
C 320 kN
D 440 kN
Answer: B. 400 kN. Using the stated factors only, 1.2 times 200 plus 1.6 times 100 equals 400 kN.
Two foundations 20 m apart settle 10 mm and 30 mm. Find angular distortion magnitude.
A 1 in 100
B 1 in 500
C 1 in 2000
D 1 in 1000
Answer: D. 1 in 1000. Differential settlement is 20 mm over 20,000 mm; the ratio is 0.001, or about 1 in 1000.
A 20,000 kg train climbs a 1% grade. Approximate grade resistance.
A 0.20 kN
B 1.96 kN
C 0.98 kN
D 19.6 kN
Answer: B. 1.96 kN. For a small grade, resistance is approximately mg times 0.01: 20,000 times 9.81 times 0.01 equals about 1.96 kN.
A structure's factored resistance is 900 kN and demand is 750 kN. Find reserve above demand.
A 150 kN
B 75 kN
C 300 kN
D 1650 kN
Answer: A. 150 kN. The numerical reserve is resistance minus demand: 900 minus 750 equals 150 kN.
Which task should be prioritized if it delays every downstream activity?
A Critical-path activity
B Noncritical float activity
C Unscheduled inspection
D Optional landscaping
Answer: A. Critical-path activity. A delay on a critical-path activity can delay project completion unless time is recovered elsewhere.
A stormwater model predicts capacity is exceeded during a design event. What is the direct response?
A Reduce survey accuracy
B Ignore the rainfall input
C Revise conveyance or storage
D Remove maintenance access
Answer: C. Revise conveyance or storage. Exceedance indicates the system needs a design response such as added conveyance, storage, source control or revised safe overflow routing.
What does differential settlement threaten first in a stiff frame?
A Concrete color
B Serviceability and cracking
C Grid frequency
D Traffic signal phase
Answer: B. Serviceability and cracking. Unequal support movement can distort a frame, causing serviceability problems and cracking before ultimate strength is necessarily reached.
A retaining wall shows water pressure buildup. Which design feature addresses drainage?
A More paint layers
B A wider traffic lane
C A softer survey datum
D Drainage layer and outlets
Answer: D. Drainage layer and outlets. A drainage layer and outlets relieve hydrostatic pressure behind the wall when properly designed and maintained.
A construction drawing conflicts with a coordinated BIM model. What is the controlled first step?
A Resolve and document the conflict
B Build both options
C Delete inspection records
D Change scope informally
Answer: A. Resolve and document the conflict. The team should raise and resolve the discrepancy through the project's formal coordination and change-control process before construction.
A concrete placement is interrupted beyond the planned sequence. What is the key concern?
A Survey scale only
B Traffic sign spacing
C Steel color
D Cold-joint location and preparation
Answer: D. Cold-joint location and preparation. An unplanned interruption can create a cold joint; location, surface preparation and structural detailing need review.
A slope's estimated resisting force is 600 kN and driving force is 400 kN. Find factor of safety.
A 0.67
B 1.0
C 1.5
D 2.5
Answer: C. 1.5. For the stated simple force ratio, factor of safety is resistance divided by driving force: 600 divided by 400 is 1.5.
An alternative costs more initially but has lower maintenance and replacement cost. Which method compares total cost fairly?
A Initial bid comparison only
B Life-cycle cost analysis
C Material color review
D Single-year budget check
Answer: B. Life-cycle cost analysis. Life-cycle cost analysis compares relevant costs across the asset service period instead of considering initial price alone.
What should an EIA mitigation hierarchy do first?
A Compensate before avoiding
B Ignore alternatives
C Avoid impacts where feasible
D Delay monitoring
Answer: C. Avoid impacts where feasible. The hierarchy generally prioritizes avoiding impacts, then minimizing, restoring and compensating for residual impacts.
A building site is in a flood-prone area. What supports climate resilience?
A Reduce drainage capacity
B Ignore future conditions
C Assess hazard and adapt design
D Remove access routes
Answer: C. Assess hazard and adapt design. Resilience begins with hazard and exposure assessment, then adapts siting, levels, drainage, structure and emergency planning.
A nonconforming concrete test result is received. What is the quality response?
A Discard the test record
B Pour over the result
C Change acceptance limits
D Record, assess and correct
Answer: D. Record, assess and correct. A nonconformance should be documented, technically assessed and resolved through approved corrective action and acceptance procedures.
A worker enters an unprotected excavation. What is the immediate priority?
A Continue the schedule
B Remove the barricade
C Stop work and control hazard
D Wait for final inspection
Answer: C. Stop work and control hazard. Work should stop until the excavation hazard is controlled using suitable protective systems and safe access.
Two drainage pipes clash with a foundation in the model. What is the main value of early coordination?
A Increase excavation risk
B Hide the design change
C Avoid field rework
D Reduce survey control
Answer: C. Avoid field rework. Resolving a clash before construction avoids rework, delay and unsafe site improvisation.
A material has low initial cost but poor durability in a marine environment. What should guide selection?
A Lowest purchase price only
B Color preference only
C Delivery date only
D Exposure and service-life performance
Answer: D. Exposure and service-life performance. Material selection should account for exposure, durability, maintenance and required service life, not only initial cost.
Why should a project change be formally controlled?
A Assess scope, cost and risk
B Remove design accountability
C Avoid stakeholder review
D Skip drawing updates
Answer: A. Assess scope, cost and risk. Change control evaluates technical, cost, schedule, safety and risk effects and updates approved project records.
A bridge maintenance program is being prioritized. What is a sound basis?
A Condition, risk and consequence
B Age alone
C Appearance alone
D Lowest inspection cost
Answer: A. Condition, risk and consequence. Prioritization should consider condition, likelihood and consequence of failure, service criticality and available resources.