A customer complaint process lists acknowledgement, investigation and response in order. This plan is a
A Strategy
B Budget
C Rule
D Procedure
Answer: D. Procedure. A procedure specifies a sequence of steps to handle recurring work.
Within that complaint process, instructions for checking a damaged item are a
A Method
B Objective
C Policy
D Programme
Answer: A. Method. A method explains how a specific task within a wider process should be performed.
A safety notice states that entry is prohibited without protective equipment. This is a
A Policy
B Rule
C Strategy
D Budget
Answer: B. Rule. A rule is a definite instruction that must be followed.
Managers may approve discounts up to five percent using their judgement. This guidance is a
A Rule
B Method
C Policy
D Programme
Answer: C. Policy. A policy guides decisions within limits while leaving some discretion.
A campaign plan lists estimated costs and sales in numerical terms. It is a
A Procedure
B Strategy
C Rule
D Budget
Answer: D. Budget. Budgets state expected results or resource use in numerical terms.
A company opens a new branch with a task list, schedule and assigned resources. This is a
A Programme
B Standing policy
C Product method
D Employee rule
Answer: A. Programme. A programme brings related tasks and resources together for a specific initiative.
A company chooses a broad plan to compete through reliable service and fast delivery. This is a
A Method
B Strategy
C Budget
D Procedure
Answer: B. Strategy. A strategy sets a broad course for achieving important organisational goals.
A logistics team aims to deliver 95 percent of orders on time. The target is an
A Rule
B Procedure
C Objective
D Method
Answer: C. Objective. The target describes a desired result and therefore is an objective.
Managers use the same leave-approval guideline throughout the year. This is a
A Single-use plan
B One-time programme
C Campaign budget
D Standing plan
Answer: D. Standing plan. A recurring guideline used across similar decisions is a standing plan.
A firm prepares a spending estimate for a single product launch. This is a
A Single-use budget
B Standing policy
C Recurring procedure
D Workplace rule
Answer: A. Single-use budget. This budget supports a specific launch rather than recurring operations.
How are a procedure and a method related?
A A procedure is numerical
B Method covers one task
C A method sets objectives
D A procedure removes all choice
Answer: B. Method covers one task. A procedure gives an ordered process, while a method explains how a particular task is done.
A manual gives the steps for processing a return and details how to test the item. It contains
A A rule and a budget
B A strategy and an objective
C A procedure and a method
D Two single-use budgets
Answer: C. A procedure and a method. The sequence is a procedure; the specific testing instructions are a method.
A guideline says to consult a supervisor, but a rule says never enter a restricted zone. Which one is stricter?
A The guideline
B The budget
C The strategy
D The rule
Answer: D. The rule. A rule is mandatory and allows little or no discretion.
Which pair is commonly classified as single-use plans?
A Programmes and budgets
B Policies and procedures
C Rules and methods
D Objectives and policies
Answer: A. Programmes and budgets. Programmes and budgets are typically prepared for specific uses.
After a selected plan begins, managers compare progress with its schedule. This is part of
A Premise development
B Follow-up action
C Alternative generation
D Objective setting
Answer: B. Follow-up action. Follow-up checks implementation and identifies deviations that may need correction.
A well-researched plan fails after an unforeseen border closure. What limitation does this reveal?
A Planning removes external risk
B Planning controls every force
C Planning cannot guarantee success
D Planning prevents change
Answer: C. Planning cannot guarantee success. External events can disrupt plans even when managers have prepared carefully.
A detailed plan prevents quick response when customers suddenly change preferences. Which limitation is shown?
A Pervasiveness
B Coordination
C Innovation
D Rigidity
Answer: D. Rigidity. Plans can limit flexibility when environmental conditions change quickly.
A manager relies on a forecast that no longer matches actual demand. What planning issue is present?
A Outdated assumptions
B Standing rules
C Numerical budgets
D Employee involvement
Answer: A. Outdated assumptions. Planning premises can become outdated when actual conditions change.
A team spends months gathering data and hiring consultants before deciding. Which limitation is most evident?
A Reduced uncertainty
B Time and cost
C Shared direction
D Control standards
Answer: B. Time and cost. Planning can consume substantial time and resources.
During follow-up, managers find costs above the approved budget and revise procurement steps. They are
A Setting initial objectives
B Developing premises
C Taking corrective action
D Generating alternatives
Answer: C. Taking corrective action. Follow-up can reveal deviations and prompt corrective action.
A manager compares feasible routes and chooses one that best meets the delivery target. This is
A Setting the objective
B Developing a premise
C Following up action
D Selecting an alternative
Answer: D. Selecting an alternative. After evaluating alternatives, management selects the most suitable course.
A company wants to expand and chooses a broad approach for competing in new markets. The approach is its
A Strategy
B Method
C Rule
D Procedure
Answer: A. Strategy. The strategy is the broad plan for achieving the company's expansion objective.
A sudden supplier shortage makes the approved plan unrealistic. What should managers do?
A Follow it without review
B Review and revise the plan
C Remove all objectives
D Stop gathering information
Answer: B. Review and revise the plan. Continuous planning allows plans to be adjusted when conditions change.
A hospital plans staffing levels while each department plans its own shifts. This reflects planning's
A Single-use nature
B Numerical nature
C Pervasive nature
D Legal nature
Answer: C. Pervasive nature. Planning is required throughout the organisation and at different levels.
Which sequence best represents the planning process?
A Evaluation, follow-up, premises, objectives, selection
B Implementation, selection, objectives, premises, review
C Alternatives, implementation, objectives, review, premises
D Objectives, premises, alternatives, evaluation, selection
Answer: D. Objectives, premises, alternatives, evaluation, selection. The process starts with objectives and premises, then identifies and evaluates alternatives before selection.