Difficulty: Easy & Basic
A fixed plan can make an organisation less flexible when conditions change. This is a limitation called
A Pervasiveness
B Rigidity
C Coordination
D Innovation
Answer: B. Rigidity. Plans can become rigid and limit an organisation's ability to respond quickly.
Why can planning be ineffective in a rapidly changing environment?
A Managers can control every change
B Plans always predict markets
C Assumptions may quickly become outdated
D Objectives cannot be changed
Answer: C. Assumptions may quickly become outdated. Rapid changes may make the assumptions behind a plan no longer valid.
A careful plan fails after an unexpected natural disaster. This shows planning
A Removes uncertainty completely
B Controls external events
C Replaces environmental analysis
D Cannot guarantee success
Answer: D. Cannot guarantee success. Uncontrollable external events can prevent a plan from succeeding.
Employees stop suggesting ideas because they must follow a detailed plan. This illustrates
A Reduced creativity
B Lower planning cost
C Improved flexibility
D Stronger forecasting
Answer: A. Reduced creativity. Overemphasis on following established plans may discourage employee creativity.
Preparing detailed forecasts and alternatives takes substantial staff time. This reflects planning's
A Pervasive nature
B Time-consuming nature
C Futuristic nature
D Decision-making benefit
Answer: B. Time-consuming nature. Collecting information and developing plans can require considerable time.
Hiring experts and gathering data to prepare a plan can make planning
A Unnecessary
B Guaranteed
C Costly
D Informal
Answer: C. Costly. Planning can involve significant costs for research, analysis and specialist input.
A firm assumes its approved plan must succeed and ignores warning signs. This is a
A First-mover advantage
B Programme budget
C Standing plan
D False sense of security
Answer: D. False sense of security. A plan may create overconfidence even though actual outcomes remain uncertain.
Staff resist a new plan because it changes familiar work routines. This illustrates
A Resistance to change
B Reduced uncertainty
C Improved coordination
D Better control
Answer: A. Resistance to change. People may resist planning when proposed changes disrupt established routines.
Which step should normally begin the planning process?
A Selecting alternatives
B Setting objectives
C Following up actions
D Implementing the plan
Answer: B. Setting objectives. The process starts by deciding what the organisation aims to achieve.
Managers estimate future demand, prices and other conditions before comparing options. They are
A Setting rules
B Measuring results
C Developing premises
D Implementing plans
Answer: C. Developing premises. Planning premises are assumptions about future conditions on which plans are based.
After objectives and assumptions are set, managers should
A Implement every possible plan
B Measure final results
C Set employee salaries
D Identify alternative courses
Answer: D. Identify alternative courses. Managers identify possible courses of action after clarifying objectives and planning premises.
A team compares the costs and benefits of each possible route. It is
A Evaluating alternatives
B Setting objectives
C Developing premises
D Following up action
Answer: A. Evaluating alternatives. Evaluating alternatives means examining their likely advantages and limitations.
Once alternatives are evaluated, management should
A Repeat the same forecast
B Select a suitable alternative
C Implement every alternative
D End all monitoring
Answer: B. Select a suitable alternative. The selected course is the one judged most suitable for the organisation's objectives.
After approving a course of action, managers should
A Create unrelated objectives
B Ignore assigned resources
C Implement the plan
D Stop communicating
Answer: C. Implement the plan. Implementation puts the chosen plan into action through decisions and resource allocation.
After a plan begins, managers check progress and make adjustments. This is
A Objective setting
B Premise development
C Alternative selection
D Follow-up action
Answer: D. Follow-up action. Follow-up helps confirm that the plan is being carried out and allows needed corrections.
Which sequence correctly starts the planning process?
A Set objectives, then premises
B Implement, then set objectives
C Follow up, then evaluate
D Select, then identify alternatives
Answer: A. Set objectives, then premises. Objectives are set before planning premises and alternatives are developed.
A forecast assumes customer demand will rise next quarter. In planning, this assumption is a
A Business rule
B Planning premise
C Method
D Programme
Answer: B. Planning premise. Premises are assumptions about future events and conditions relevant to planning.
A company considers online sales, retail stores and wholesale distribution. It is
A Evaluating final results
B Setting a policy
C Identifying alternatives
D Following a rule
Answer: C. Identifying alternatives. These are alternative courses of action for reaching the company's objectives.
A manager rejects a low-cost plan because it harms product quality. This is
A Developing premises
B Implementing the plan
C Setting objectives
D Evaluating alternatives
Answer: D. Evaluating alternatives. Evaluation considers multiple consequences, not only the lowest cost.
A selected plan names staff, resources and deadlines. The next major step is
A Implementation
B Premise setting
C Alternative generation
D Objective revision
Answer: A. Implementation. Once a plan is selected, it must be translated into assigned action.
During follow-up, managers find a supply delay and revise task dates. This is
A Objective setting
B Corrective action
C Alternative generation
D Policy publication
Answer: B. Corrective action. Follow-up can reveal deviations that require corrective adjustments.
Why do managers develop premises before selecting a plan?
A They record completed outcomes
B They replace business objectives
C They frame future assumptions
D They guarantee accurate forecasts
Answer: C. They frame future assumptions. Premises provide the assumptions used to assess future courses of action.
A planning team lists three ways to meet a delivery target. What should it do next?
A Set the target again
B Follow up the delivery
C Close the planning process
D Evaluate the alternatives
Answer: D. Evaluate the alternatives. After identifying alternatives, managers examine their likely suitability.
A manager chooses an action without comparing available options. Which planning step was skipped?
A Evaluating alternatives
B Setting objectives
C Implementing the plan
D Following up action
Answer: A. Evaluating alternatives. Alternatives should be evaluated before selecting a course of action.
A firm compares actual progress with its chosen plan and acts on delays. This is
A Premise setting
B Follow-up action
C Objective selection
D Programme budgeting
Answer: B. Follow-up action. Follow-up reviews implementation and supports timely correction.