Work queues before the zipper station while the station after it is often idle. What likely limits sewing output?

A Pressing area lighting
B Final carton width
C Zipper station capacity
D Marker paper strength

If the pattern pieces use 10.2 m² of a 12 m² marker, calculate marker efficiency.

A 75%
B 102%
C 15%
D 85%

If two fabric roll groups differ slightly in shade, what practice helps prevent mismatched matching panels?

A Raise needle speed only
B Mix all cut plies randomly
C Use deeper cutting notches
D Separate and trace bundles

During a 460-minute shift, 230 garments are required. What is customer takt time?

A 0.5 min/garment
B 230 min/garment
C 2 min/garment
D 4 min/garment

On a knit edge that stretches while being overlocked, what machine adjustment may reduce wave formation?

A Smaller bobbin case only
B Lower fusing temperature
C Wider paper marker
D Differential feed adjustment

Fabric length per ply is 9.6 m and the marker contains eight garments. What is length per garment before other losses?

A 1.60 m
B 1.20 m
C 0.83 m
D 76.80 m

Operator time totals 2,000 min and the line earns 1,500 standard minutes. Find line efficiency using earned time divided by labour time.

A 75%
B 25%
C 50%
D 133.3%

Fabric grainlines are tilted inconsistently across pieces of the same leg panel. Which issue can appear after assembly and washing?

A Higher marker width
B More stitch holes always
C Less sewing thread use
D Twisted garment panels

Observed sewing time is 0.80 min at a performance rating of 125%. What is normal time before allowances?

A 1.00 min
B 1.25 min
C 0.64 min
D 0.80 min

Four operators work 7.5 h each and complete 180 garments. What is output per labour hour?

A 24 garments/h
B 6 garments/h
C 45 garments/h
D 3 garments/h

Calculate total area for a marker that is 1.50 m wide and 8 m long.

A 5.33 m²
B 9.5 m²
C 12 m²
D 120 m²

Where many garments show the same skipped stitch defect, what is a useful first check on the machine?

A Needle condition and timing
B Pressing table colour
C Marker plot scale
D Carton label placement

Daily demand cannot change, but available working minutes fall. What happens to customer-demand takt time?

A It equals seam allowance
B It gets longer
C It gets shorter
D It remains unchanged

If a sewing operation takes 48 seconds per garment, what is its theoretical hourly capacity?

A 48 garments/h
B 75 garments/h
C 125 garments/h
D 60 garments/h

Fusible interlining peels even though the press meets target temperature. Which two settings also need review?

A Bottle volume and shade
B Cone shape and colour
C Marker length and width
D Dwell time and pressure

If an operator turns out 20 accepted garments with a 6 minute standard each, how many standard minutes are earned?

A 20 min
B 26 min
C 3.33 min
D 120 min

Why record machine work time separately from waiting time in a sewing study?

A Make every station identical
B Distinguish processing from delay
C Remove checking activities
D Increase the seam length

With six garments per marker and 45 usable plies, how many garment sets can be cut?

A 270
B 51
C 45
D 7.5

The operator switches to a thicker fabric without changing the needle. Which compatibility should be checked before bulk sewing?

A Package and loom size
B Floor colour and trim
C Roll label and carton
D Needle, thread and fabric

If normal time is 2 min and allowance is 15% of normal time, what is the standard time?

A 2.15 min
B 1.70 min
C 2.30 min
D 2.35 min

Video shows an automatic sewing attachment needs a long setup but stitches quickly. Which time category rises most per garment for small batches?

A Setup time per garment
B Marker length per ply
C Needle count per seam
D Machine speed per stitch

Forty plies each require 5 m plus 0.10 m end loss. How much fabric is spread?

A 204 m
B 240 m
C 200 m
D 201 m

At finishing, one garment has measurements within tolerance but the zipper will not close. Which separate check captures the issue?

A Carton weight check
B Yarn count confirmation
C Functional inspection
D Fabric width inspection only

Among sequential stations with hourly capacities 90, 80 and 100, what maximum steady output can the line sustain without added parallel capacity?

A 90 garments/h
B 80 garments/h
C 270 garments/h
D 100 garments/h

At 4 stitches/cm, how many stitches are needed along a 180 cm seam?

A 45
B 720
C 184
D 180