Suppose nondelivery raises the market price of replacement goods. Which loss may qualify?
A Every future business loss
B A stranger's expense
C A remote forecast
D Difference in market price
Answer: D. Difference in market price. Section 73's illustration uses the difference between contract and market price at delivery.
Suppose a buyer claims a secret downstream loss never disclosed at formation. What may apply?
A Automatic Section 74 award
B Public-bond exception
C Remote loss exclusion
D Section 75 entitlement
Answer: C. Remote loss exclusion. Section 73 excludes remote loss; undisclosed consequential loss may be too remote.
When ordinary repair expense follows a breach, what should be examined first?
A A witness's view
B Natural causal connection
C The promisor's income
D The contract's title
Answer: B. Natural causal connection. Section 73 requires damage caused by breach and naturally arising or contemplated.
If a penalty clause names βΉ50,000 but actual damage is unproved, what may be awarded?
A Reasonable amount up to cap
B Automatic βΉ50,000
C Nothing in every case
D Double the named amount
Answer: A. Reasonable amount up to cap. Section 74 permits reasonable compensation without proved damage, capped at the named amount.
If reasonable compensation is βΉ20,000 under a βΉ50,000 clause, what is not automatic?
A A capped award
B Reasonable compensation
C A breach finding
D Full βΉ50,000 award
Answer: D. Full βΉ50,000 award. The named sum is a ceiling, not an automatic award.
What may a sharp post-breach interest increase be treated as?
A A completed gift
B Remote damage
C Penalty
D A third-party debt
Answer: C. Penalty. Section 74 says increased interest from default may be a penalty stipulation.
Can a singer who rightfully rescinds after loss seek compensation under Section 75?
A Section 74
B Section 75
C Section 39
D Section 62
Answer: B. Section 75. Section 75 allows compensation for damage sustained through nonfulfilment after rightful rescission.
Suppose a supplier refuses the entire promise before its due date. Which section supports termination?
A Section 39
B Section 73
C Section 74
D Section 75
Answer: A. Section 39. Section 39 covers total refusal or disabling oneself from performance.
When a supplier misses an essential deadline, what option may the buyer have?
A Demand automatic penalty
B Lose all remedies
C Force late acceptance
D Avoid the contract
Answer: D. Avoid the contract. Section 55 makes the contract voidable at the promisee's option when time was essential.
When a buyer accepts late delivery without reserving damages, what follows for delay compensation?
A Full penalty is due
B Contract is void
C Delay claim barred
D Promisor pays double
Answer: C. Delay claim barred. Section 55 bars delay compensation when the promisee accepts late performance without notice.
How may Section 74 apply to a breached public-duty bond with a stated sum?
A Remote loss rule
B Whole sum exception
C No compensation rule
D Ordinary market rule
Answer: B. Whole sum exception. Section 74's exception may require the whole sum for qualifying public-duty bonds.
If breach causes a loss that was neither usual nor known when contracting, what is likely?
A Not recoverable if remote
B Always recoverable
C Automatic penalty
D Section 75 damages
Answer: A. Not recoverable if remote. Section 73 excludes remote or indirect loss not naturally arising or known as likely.
Which amount limits a Section 74 award?
A Any amount demanded
B Twice the price
C Only court costs
D Stipulated sum or penalty
Answer: D. Stipulated sum or penalty. Section 74 caps reasonable compensation at the named sum or penalty.
What should a court consider when valuing inconvenience after breach?
A The breacher's reputation
B A later unrelated loss
C Available ways to remedy
D The parties' ages
Answer: C. Available ways to remedy. Section 73's Explanation requires considering means available to remedy inconvenience.
Even after finding a substitute, what costs might a buyer still recover?
A Every lost opportunity
B Trouble and expense
C A remote future profit
D A penalty by default
Answer: B. Trouble and expense. The Act's illustration allows compensation for trouble and expense despite a suitable substitute.
What is the causal requirement for Section 73 damages?
A Breach caused the loss
B Loss preceded contract
C A witness confirmed it
D Penalty was written
Answer: A. Breach caused the loss. Section 73 ties compensation to loss caused by the breach.
Which loss is more likely recoverable under Section 73?
A Undisclosed remote loss
B Unrelated third-party loss
C Imagined future income
D Known likely special loss
Answer: D. Known likely special loss. The parties' knowledge at formation can bring likely special loss within Section 73.
Does a penalty clause replace proof of breach?
A Yes, always
B Only for public bonds
C No, breach is required
D Only if written
Answer: C. No, breach is required. Section 74 applies only when the contract has been broken.
What does Section 74 require even when damages are unproved?
A Automatic full penalty
B Reasonable compensation
C No remedy
D Punishment of promisor
Answer: B. Reasonable compensation. The section permits reasonable compensation, not an automatic punitive award.
If a contract is rightfully rescinded, what kind of loss can Section 75 cover?
A Damage through nonfulfilment
B Every unrelated loss
C A witness's costs
D A later price change
Answer: A. Damage through nonfulfilment. Section 75 covers damage sustained through the contract's nonfulfilment.
What may a complaining party receive when breach triggers a penalty clause?
A The full clause automatically
B Double damages always
C Only nominal damages
D Reasonable capped compensation
Answer: D. Reasonable capped compensation. Section 74 permits reasonable compensation not exceeding the stipulated amount.
Why does Section 73 exclude remote loss?
A It cancels every contract
B It requires a penalty
C It limits breach compensation
D It protects a witness
Answer: C. It limits breach compensation. The statute limits compensation to natural or contemplated loss, excluding remote and indirect damage.
Which step can reduce an inconvenience loss estimate?
A Ignoring substitute options
B Using available remedies
C Increasing the named penalty
D Adding unrelated damages
Answer: B. Using available remedies. Section 73 requires available means of remedying inconvenience to be considered.
What does a rightful rescinder gain under Section 75?
A Right to claim compensation
B Automatic full contract price
C A criminal sanction
D An unconditional penalty
Answer: A. Right to claim compensation. The section grants compensation for damage caused by nonfulfilment.
Which legal measure best separates Section 73 from Section 74?
A Offer versus acceptance
B Age versus capacity
C Silence versus fraud
D Remoteness versus penalty cap
Answer: D. Remoteness versus penalty cap. Section 73 limits recoverable losses by causation and remoteness; Section 74 caps reasonable compensation under a stipulation.