Difficulty: Medium
What may a promisee do after total refusal to perform?
A Demand registration
B Transfer the promise
C End the contract
D Change consideration
Answer: C. End the contract. Section 39 allows the promisee to put an end to the contract after total refusal or disabling.
When can refusal amount to anticipatory breach?
A Only after judgment
B Before performance is due
C After full performance
D Only after registration
Answer: B. Before performance is due. A clear refusal or disabling before the due date can permit the promisee to end the contract.
What may count as total refusal under Section 39?
A Disabling oneself from performance
B A minor delay only
C A price negotiation
D A delivery receipt
Answer: A. Disabling oneself from performance. Section 39 covers refusal to perform wholly or disabling oneself from performance.
What may block the promisee from ending the contract?
A A market price drop
B A witness's absence
C A later promise
D Acquiescence in continuation
Answer: D. Acquiescence in continuation. Section 39 preserves the contract if the promisee signifies acquiescence in continuation.
Which section governs failure at a fixed time?
A Section 39
B Section 73
C Section 55
D Section 74
Answer: C. Section 55. Section 55 addresses failure to perform at a fixed time.
When does missed timing make a contract voidable?
A Whenever any date passes
B When time was essential
C Only after a penalty
D When payment is partial
Answer: B. When time was essential. Section 55 makes the contract voidable when time was intended to be essential.
What if time was not essential?
A Delay alone not voidable
B Contract always becomes void
C Promisee loses damages
D Penalty is automatic
Answer: A. Delay alone not voidable. Section 55 says delay does not make the contract voidable if time was not essential.
What may follow nonessential delay?
A Automatic rescission
B Punitive damages
C A fresh contract
D Compensation for loss
Answer: D. Compensation for loss. The promisee may claim compensation for loss occasioned by delay.
When must delayed-performance compensation be reserved?
A Before contract formation
B After a final appeal
C At acceptance of delay
D Only by registration
Answer: C. At acceptance of delay. The promisee must give notice at the time of accepting delayed performance.
What if late performance is accepted without notice?
A Full penalty is due
B Delay compensation unavailable
C Contract is automatically void
D Promisor owes double
Answer: B. Delay compensation unavailable. Section 55 bars delay compensation when late performance is accepted without notice.
Who may claim under Section 75?
A Person rightfully rescinding
B Any unrelated party
C Defaulting party only
D A witness
Answer: A. Person rightfully rescinding. Section 75 gives compensation to a person who rightfully rescinds.
What damage can Section 75 compensate?
A Every remote loss
B A stranger's loss
C A future price forecast
D Damage from nonfulfilment
Answer: D. Damage from nonfulfilment. Section 75 covers damage sustained through nonfulfilment of the contract.
Which section provides compensation after rightful rescission?
A Section 73
B Section 39
C Section 75
D Section 55
Answer: C. Section 75. Section 75 addresses compensation for a party rightfully rescinding.
What may a promisee do after a party disables itself?
A Must continue performance
B Put an end to contract
C Transfer the debt
D Register the breach
Answer: B. Put an end to contract. Section 39 allows ending the contract when a party disables itself from performing wholly.
How can a promisee accept late performance and preserve a claim?
A Give notice at acceptance
B Send notice years later
C Refuse every delivery
D Change the penalty
Answer: A. Give notice at acceptance. Section 55 requires contemporaneous notice of the intent to claim delay compensation.
Which factor separates essential from nonessential time?
A The buyer's income
B The court's schedule
C The market price alone
D Parties' contractual intention
Answer: D. Parties' contractual intention. Section 55 turns on whether the parties intended time to be essential.
What may a party claim after rightful termination for breach?
A Automatic criminal fine
B The entire price always
C Compensation for damage
D A new contract by law
Answer: C. Compensation for damage. Section 75 permits compensation for damage sustained through nonfulfilment.
Does total refusal always let a promisee terminate?
A Yes, without exception
B Not after acquiescence
C Only after a trial
D Only if written
Answer: B. Not after acquiescence. Section 39 preserves the agreement if the promisee acquiesces in its continuance.
Which breach may permit termination under Section 39?
A Refusal to perform wholly
B Minor price disagreement
C Request for more time
D An ordinary inquiry
Answer: A. Refusal to perform wholly. Section 39 addresses refusal to perform the promise wholly or disabling performance.
What must a delay-claim notice communicate?
A Intent to change price
B Intent to register deed
C Intent to assign rights
D Intent to claim compensation
Answer: D. Intent to claim compensation. Section 55 requires notice that compensation for delay is intended.
Can rightful rescission itself support a compensation claim?
A No, never
B Only under Section 74
C Yes, under Section 75
D Only after registration
Answer: C. Yes, under Section 75. Section 75 grants compensation to a person who rightfully rescinds.
What is the result when time was essential and performance is late?
A Contract void automatically
B Contract voidable by promisee
C No damages possible
D Promisor may rescind only
Answer: B. Contract voidable by promisee. Section 55 makes the contract voidable at the promisee's option.
When can a promisee continue despite repudiation?
A By words or conduct
B Only through silence
C Only after court order
D Never under Section 39
Answer: A. By words or conduct. Section 39 recognizes acquiescence signified by words or conduct.
What is one remedy for a rightful rescinder?
A Full penalty automatically
B A witness fee
C A guaranteed profit
D Compensation for damage
Answer: D. Compensation for damage. Section 75 provides compensation for damage caused by nonfulfilment.
Which option best reflects Section 39's choice?
A Always terminate immediately
B Never terminate
C Terminate unless acquiescing
D Only seek registration
Answer: C. Terminate unless acquiescing. The promisee may end the contract unless they acquiesce in its continuation.