Software Engineering MCQs (Set-4)

Given E=14, N=12, and P=1, complexity is?

A 4
B 3
C 5
D 6

PERT estimates are O=2, M=5, P=8; expected time is?

A 4
B 6
C 5
D 7

Suppose loss is $40,000 with probability 25%; exposure is?

A $1,000
B $5,000
C $40,000
D $10,000

In UML, Β«includeΒ» usually represents what?

A Optional behavior extension
B Mandatory reused behavior
C A class inheritance
D A deployment node

Unlike Β«includeΒ», Β«extendΒ» represents what?

A Mandatory shared behavior
B A data type
C A deployment package
D Optional conditional behavior

MC/DC coverage requires each condition to do what?

A Independently affect outcome
B Execute once only
C Pass every test
D Use each data type

Production logs, metrics, and traces support what?

A Requirements elicitation
B Source formatting
C Operational monitoring
D Budget estimation

If a dependency is failing, a circuit breaker helps by?

A Deleting its source
B Stopping repeated calls
C Changing the API
D Disabling all tests

Blue-green deployment normally switches traffic between what?

A Two production environments
B Two code editors
C Two test cases
D Two backlog items

Canary releases first send traffic to what?

A All users at once
B Only test machines
C No production users
D Small user subset

Balancing low latency against strong isolation is an example of?

A Requirements elicitation
B Code compilation
C Quality attribute trade-off
D Unit test isolation

Fault-tolerant designs commonly use what?

A Single points of failure
B Redundancy and failover
C Untracked local changes
D Unverified assumptions

API backward compatibility helps which users?

A Only future developers
B Only test managers
C Unrelated services
D Existing clients

Before approving a change, impact analysis identifies what?

A Affected components and tests
B Only the change author
C Unrelated project budgets
D All future releases

A risk response that removes the threat is called?

A Risk acceptance
B Risk transfer
C Risk avoidance
D Risk monitoring

In Scrum 2020, the Sprint Goal gives the Sprint what?

A Fixed scope guarantee
B Single objective
C Release approval
D Testing standard

Under the Scrum Guide, an Increment must meet what?

A Definition of Done
B A fixed story count
C A manager's estimate
D Every future requirement

In a layered design, why constrain dependency direction?

A Increase circular imports
B Share every database
C Remove module boundaries
D Limit cross-layer coupling

Refactoring changes internal structure while preserving what?

A Every line number
B The release date
C Observable behavior
D The project budget

Software reliability concerns failure-free operation under what?

A Any possible environment
B Stated conditions and time
C Unlimited duration
D Unknown requirements

At 99.9% availability over 30 days, downtime is about?

A 4 minutes
B 7 hours
C 43 hours
D 43 minutes

Which item can be managed as a configuration item?

A Tracked project artifact
B Unrecorded conversation
C Personal preference
D Temporary thought

Which risk response lowers probability or impact?

A Risk avoidance
B Risk transfer
C Risk mitigation
D Risk acceptance

A test using forecast peak traffic is what type?

A Mutation test
B Load test
C Usability review
D Static analysis

Technical debt describes future cost from what?

A User acceptance tests
B Stable interfaces
C Automated releases
D Expedient design choices