Difficulty: Hard
During peak demand, response slows as users increase. Which design quality needs attention?
A Portability
B Usability
C Confidentiality
D Scalability
Answer: D. Scalability. Scalability is the ability to handle growth in workload or users.
Two applications exchange mismatched dates and codes. Which work resolves this?
A Data mapping
B Interface styling
C User training
D Capacity planning
Answer: A. Data mapping. Data mapping aligns fields and formats between systems.
A report counts one customer twice across systems. What is most needed?
A More dashboards
B Batch processing
C Master data matching
D Local identifiers
Answer: C. Master data matching. Master data matching helps recognize records for the same customer across sources.
Updates must appear within milliseconds. Which processing style is indicated?
A Scheduled batch processing
B Real-time processing
C Manual reconciliation
D Monthly consolidation
Answer: B. Real-time processing. Real-time systems process or respond to events with minimal delay.
Records are correct but arrive late. Which information quality is compromised?
A Completeness
B Consistency
C Availability
D Timeliness
Answer: D. Timeliness. Information may be accurate yet lose value when it is not timely.
If one server fails while a standby node continues service, what occurred?
A Data cleansing
B Load balancing
C Failover
D Capacity testing
Answer: C. Failover. Failover shifts operations to a standby component after a failure.
Which design choice removes a single point of failure?
A Redundant infrastructure
B Centralized bottleneck
C Manual approval
D Shared password
Answer: A. Redundant infrastructure. Redundancy provides alternative components if one part fails.
To recover after corrupted data, which resource is essential?
A A user interface
B Verified backup
C A project charter
D A report template
Answer: B. Verified backup. A verified backup can restore data after corruption or loss.
How should information-system access match each employee’s duties?
A Open permissions
B Shared administrator accounts
C Public access links
D Role-based permissions
Answer: D. Role-based permissions. Role-based permissions grant access according to assigned job responsibilities.
An auditor needs evidence of record changes. Which control helps?
A A dashboard filter
B A file export
C Audit trail
D A screen reader
Answer: C. Audit trail. An audit trail records who changed information and when.
Before cloud migration, which concern must be assessed with business needs?
A Screen resolution
B Data residency obligations
C Printer access
D Meeting schedules
Answer: B. Data residency obligations. Data residency requirements can govern where information is stored and processed.
Which decision compares internal software development with buying a package?
A Make-or-buy analysis
B Data normalization
C User acceptance testing
D Incident response
Answer: A. Make-or-buy analysis. Make-or-buy analysis compares developing a solution with acquiring one.
A new application cannot exchange data with ERP. Which risk is most direct?
A Improved scalability
B Better availability
C More usability
D Operational incompatibility
Answer: D. Operational incompatibility. Poor integration can prevent the system from supporting connected operations.
How can teams limit unapproved feature expansion during a project?
A Data migration
B Network segmentation
C Scope change control
D User authentication
Answer: C. Scope change control. Scope change control evaluates and approves proposed project changes.
Which test checks interactions among connected system components?
A Unit testing
B Integration testing
C Usability testing
D Load forecasting
Answer: B. Integration testing. Integration testing checks whether connected components work together.
Why trace requirements to tests before acceptance?
A Verify coverage and acceptance
B Increase software size
C Avoid user review
D Remove test evidence
Answer: A. Verify coverage and acceptance. Traceability helps confirm that requirements are tested and acceptance criteria are met.
A redesigned system excludes staff with disabilities. Which attribute is missing?
A Maintainability
B Interoperability
C Scalability
D Accessibility
Answer: D. Accessibility. Accessibility enables people with disabilities to use the system.
What helps prevent vendor lock-in when selecting cloud services?
A More proprietary formats
B Longer contracts
C Portability planning
D Single-provider customization
Answer: C. Portability planning. Portability planning considers how data and workloads can move between services.
Which approach protects real customer details in test data?
A Data masking
B Open replication
C Public sharing
D Unfiltered export
Answer: A. Data masking. Data masking substitutes or obscures sensitive values used for testing.
An MIS improves each department but harms company-wide results. What risk is shown?
A Operational continuity
B Local optimization
C Data availability
D System portability
Answer: B. Local optimization. Local optimization can conflict with organization-wide goals.
Which governance practice assigns owners for data accuracy?
A Network routing
B User interface testing
C Batch scheduling
D Data stewardship
Answer: D. Data stewardship. Data stewardship assigns responsibility for data quality and definitions.
A release may disrupt many departments. Which deployment reduces exposure?
A Single cutover only
B Uncontrolled rollout
C Phased rollout
D Immediate decommissioning
Answer: C. Phased rollout. A phased rollout limits how much of the organization is affected at once.
What analysis includes acquisition, transition, and operating costs?
A System boundary analysis
B Total cost of ownership
C Data flow mapping
D User acceptance testing
Answer: B. Total cost of ownership. Total cost of ownership considers costs across acquisition and operation.
System outputs cannot be reproduced consistently. What should be reviewed?
A Data lineage and logic
B Logo placement
C User seating
D Printer settings
Answer: A. Data lineage and logic. Lineage and processing logic help explain how results were produced.
How should a critical system respond if its main site is disabled?
A Wait for manual rebuilding
B Delete the recovery plan
C Continue from stale files
D Activate recovery site
Answer: D. Activate recovery site. A recovery site can support continuity when the primary site is unavailable.