Difficulty: Easy & Basic
A factory sets a target of 500 units per day. This is
A Measuring actual output
B Setting a standard
C Analysing deviations
D Taking corrective action
Answer: B. Setting a standard. A target for expected output is a performance standard.
A supervisor records that today's output was 470 units. This is
A Setting a standard
B Selecting an alternative
C Measuring actual performance
D Correcting a deviation
Answer: C. Measuring actual performance. Recording actual output measures performance.
The manager compares 470 actual units with the 500-unit target. This is
A Setting objectives
B Hiring employees
C Developing a budget
D Comparing performance
Answer: D. Comparing performance. Comparison identifies the difference between actual output and the standard.
After finding a shortfall, managers investigate its cause. This is
A Analysing deviations
B Setting standards
C Measuring output
D Issuing an offer
Answer: A. Analysing deviations. Analysis determines why performance differs from the standard.
A manager adjusts machine maintenance after identifying equipment failures. This is
A Comparing performance
B Taking corrective action
C Setting a target
D Measuring output
Answer: B. Taking corrective action. Corrective action addresses a cause of the performance shortfall.
Which sequence represents the control process?
A Measure, act, compare, hire, review
B Act, compare, measure, recruit, stop
C Set, measure, compare, analyse, act
D Analyse, set, act, hire, compare
Answer: C. Set, measure, compare, analyse, act. The control process moves from setting standards through measurement, comparison, analysis and action.
A service centre sets a maximum wait time before examining customer queues. It is
A Measuring actual performance
B Analysing deviations
C Taking corrective action
D Setting standards
Answer: D. Setting standards. The expected wait-time limit is a performance standard.
A manager reviews daily reports to record actual delivery times. This is
A Measuring actual performance
B Setting a standard
C Analysing causes
D Correcting the process
Answer: A. Measuring actual performance. Actual delivery times are being measured from performance reports.
Actual delivery is three days late compared with the target. The difference is a
A Standard
B Deviation
C Objective
D Budget
Answer: B. Deviation. A deviation is the gap between actual performance and the established target.
A manager finds that a shortage of trained workers caused delays. This is
A Comparing performance
B Setting standards
C Analysing deviations
D Measuring output
Answer: C. Analysing deviations. The manager is identifying the cause of the deviation.
A company retrains staff after finding errors caused by unfamiliar software. This is
A Performance measurement
B Standard setting
C Deviation comparison
D Corrective action
Answer: D. Corrective action. Retraining addresses a cause of errors and is corrective action.
A manager focuses attention on the few areas critical to success. This is
A Critical point control
B Management by exception
C Personal observation
D Budget setting
Answer: A. Critical point control. Critical point control directs attention to key result areas.
Only deviations beyond allowed limits are reported to senior managers. This is
A Critical point control
B Management by exception
C Standard setting
D Performance measurement
Answer: B. Management by exception. Management by exception focuses attention on significant deviations beyond permitted limits.
Why does management by exception save managerial time?
A It measures every activity daily
B It removes performance standards
C It highlights significant deviations
D It avoids corrective action
Answer: C. It highlights significant deviations. Managers can focus on important exceptions instead of reviewing every minor variation.
A firm monitors safety, quality and delivery as its key result areas. It uses
A Management by exception
B Job evaluation
C Informal communication
D Critical point control
Answer: D. Critical point control. Critical point control identifies the areas that are most important for success.
A minor difference falls within the accepted tolerance range. The manager should usually
A Continue routine monitoring
B Change every standard
C Stop measuring performance
D Replace the department
Answer: A. Continue routine monitoring. Small deviations within acceptable limits may not require corrective action.
A large deviation appears in a critical area. Managers should
A Ignore it until year-end
B Investigate and respond
C Change all employees
D Stop using standards
Answer: B. Investigate and respond. Significant deviations in critical areas require analysis and appropriate action.
A standard says 'improve quality' without specifying a measurable level. What is the problem?
A Actual results are corrected
B The deviation is critical
C The standard is unclear
D Management by exception begins
Answer: C. The standard is unclear. Standards should be clear enough to measure actual performance.
A company compares actual sales with its planned sales target. It is
A Setting a new market
B Measuring employee morale
C Conducting recruitment
D Comparing results with standards
Answer: D. Comparing results with standards. The sales target is the standard used for comparison.
A manager finds repeated late deliveries and examines transport records. This is
A Analysing the deviation
B Setting a standard
C Measuring actual output
D Taking an offer
Answer: A. Analysing the deviation. Examining records to find the cause is deviation analysis.
The cause is an inefficient route, so the firm redesigns delivery schedules. This is
A Standard setting
B Corrective action
C Performance measurement
D Exception reporting
Answer: B. Corrective action. Changing an inefficient route addresses the cause of late deliveries.
A quality manager checks only the production stages with the greatest effect on defects. This is
A Management by exception
B Employee selection
C Critical point control
D Financial planning
Answer: C. Critical point control. Critical point control focuses monitoring on areas central to desired results.
A report flags only cost overruns beyond a set threshold. This is
A Critical point control
B Setting objectives
C Job rotation
D Management by exception
Answer: D. Management by exception. Management by exception highlights deviations that exceed a defined limit.
Managers should analyse a deviation before choosing action because
A Its cause guides the remedy
B All deviations have one cause
C Standards are always wrong
D Measurement is unnecessary
Answer: A. Its cause guides the remedy. Understanding the cause helps managers select suitable corrective action.
When no significant deviation exists, a manager should
A Remove the standards
B Maintain monitoring
C Cancel the plan
D Take unrelated action
Answer: B. Maintain monitoring. Control is ongoing even when results are within acceptable limits.