Work Rate
- A worker completing one job in x days has rate 1/x job per day.
Combined Rates
- Add independent workers’ rates when they work together.
Completion Time
- Time = remaining work ÷ combined rate.
Efficiency
- For the same job, efficiency is inversely proportional to completion time.
Work Units
- A common multiple of individual completion times can serve as total work units.
Alternating Work
- Calculate the output of a complete repeating cycle before the final partial cycle.
Remaining Work
- Subtract completed work from one full job.
Stages
- Treat each stage separately when workers join or leave.